DETAILS OF PROJECTS FUNDED UNDER ASIDE SCHEME OF GOVT. OF INDIA IN KERALA
|
| Sl No |
Name of the Projects |
Implementing Agency |
Total Project cost
(Rs. in lakhs) |
Aside Assistance
(Rs. In lakhs) |
State Govt. stake (Rs. in lakhs) |
Private Sector (Rs. in lakhs) |
Amount Disbursed (ASIDE)
Rs. in lakhs |
Project Status |
| 1 |
Setting up of 30 Nos.of Pre-Processing centre 2002-03 |
MPEDA |
900 |
90 |
360 |
450 |
90 |
Completed |
| 2 |
Up-gradation of Cochin Fishing Harbours2002-03 |
MPEDA |
170 |
170 |
--- |
--- |
170 |
Completed |
| 3 |
Up-gradation of MPEDA Laboratory2002-03 |
MPEDA |
140 |
140 |
--- |
--- |
140 |
Completed |
| 4 |
Setting up of a full fledged Laboratory at Aroor 2002-03 |
SEAI |
350 |
315 |
--- |
35 |
315 |
Completed |
| 5 |
Water supply scheme for KINFRA food Park 2002-03 |
KINFRA |
725 |
362.5 |
362.5 |
--- |
362.5 |
Completed |
| 6 |
Expansion of Trivandrum Air Cargo Complex |
KSIE |
391 |
195.5 |
195.5 |
--- |
195.5 |
Completed |
| 7 |
Augmentation of testing Laboratory at CEPC, Kollam 2002-03 |
CEPC |
100 |
100 |
--- |
--- |
100 |
Completed |
| 8 |
Electronic Weigh Bridge at Cochin Port 2002-03 |
CPT |
10 |
10 |
--- |
--- |
10 |
Completed |
| 9 |
Animation Zone in KINFRA Film & Video Park 2003-04 |
KINFRA |
1603 |
800 |
803 |
--- |
800 |
Completed |
| 10 |
Up-gradation of Munambam Fisheries Harbour 2005-06 |
MPEDA |
227 |
227 |
--- |
--- |
227 |
Completed |
| 11 |
Up-gradation of Electricity Distribution system in the town of Export excellence at Cherthala Taluk 2004-05 |
SEFAI |
20 |
12.75 |
--- |
7.25 |
12.75 |
Completed |
| 12 |
Development of Infrastructure facilities at industrial estate changanacherry 2004-05 |
RPSIA |
40 |
36 |
--- |
4 |
36 |
Completed |
| 13 |
Screw pine craft export promotion in Thrissur Dist 2005-06 |
KIDS |
25.32 |
19.32 |
--- |
6 |
19.32 |
Completed |
| 14 |
Setting up of an ICD at Kottayam 2005-06 |
KPACT |
936 |
740 |
--- |
196 |
740 |
Completed |
| 15 |
Construction of 11KV Feeder line from Chellanam Sub station to the sea Food & peeling shed Units at Ezhupunna Panchayat 2007-08 |
SEAI |
85 |
63.75 |
--- |
21.25 |
63.75 |
Completed |
| 16 |
Augmentation of infrastructure facilities at KINFRA Export promotion industrial park 2006-07 |
KEPIP |
1150 |
751.77 |
398.23 |
--- |
751.77 |
Completed |
| 17 |
External Infrastructure development of Hi-tech Park Kalamassery (1st Phase) 2005-06 |
KINFRA |
1935 |
1935 |
--- |
--- |
1935 |
Completed |
| 18 |
Enhancement of Infrastructure facility of SEZ at KINFRA Film and Video Park, Thiruvananthapuram 2007-08 |
KINFRA |
900 |
600 |
300 |
--- |
600 |
Completed |
| 19 |
Additional infrastructure facilities at Air cargo Complex at Calicut 2006-07 |
Kerala State Industrial Enterprises |
310 |
155 |
155 |
--- |
155 |
Completed |
| 20 |
Export based Apparel Park in Industrial Growth Center, Kannur 2007-08 |
KSIDC |
700 |
350 |
350 |
--- |
350 |
Completed |
| 21 |
Rural export promotion apparel park, Thalikulam2009-10 |
Thalikulam Vikas Trust |
535 |
412 |
|
123 |
412 |
Completed |
| 22 |
Dyeing and Winding Plant in Textile Centre, Kannur (KTC) 2009-10 |
KINFRA |
1065 |
900 |
165 |
--- |
900 |
Completed |
| 23 |
Truck Parking Terminal Wellingdon Island |
Wellingdon Island Parking Yard Pvt Ltd |
526 |
288 |
--- |
238 |
288 |
Completed |
| Sl No |
Name of the Projects |
Implementing Agency |
Total Project cost (Rs.in lakh) |
Aside Assistance (Rs. in lakhs) |
State Govt. stake (Rs. In lakhs) |
Private Sector stake (Rs. In lakhs) |
Amount Disbursed (ASIDE) Rs. in lakhs |
Balance to be paid |
Project Status |
| 1 |
Rural Export Promotion Apparel Park, Rajakumari, Idukki |
Kinfra International Apparel Park |
700 |
300 (08.03.2011) |
400 |
Nil |
300 |
Nil |
Under implementation |
| 2 |
Container Freight Station at Eloor, Kalamassery, Kochi |
KSIE |
4600.98 |
1000 |
3600.98 |
|
1000 |
Nil |
Under implementation |
Total No. of Project - 25